RC works progresses at the station's concourse level. Structure around entrance B has surfaced to the basement roof level with formwork installation ongoing in preparation for the first roof slab cast.


Mount Pleasant Station
Entrance B
RC works for concourse to roof slab structure. Formwork installation ongoing for the roof slab around the entrance.

Internal walls for ECS and ventilation service corridors cast at concourse level
Concourse unpaid & paid area boundary (south end)
Station area (north end)
Opening in concourse slab down to the mezzanine & platform levels. The escalator landing pits for escalator 5 and 6 between the concourse and mezzanine levels are carved out in the concourse slab

RC wall works for service rooms at the north end
Entrance A


Tunnelling works for the second drive set to complete within the next few weeks.