Friday 10 November 2017

November Tunnel Progress

Bored tunnelling works progresses across the line, with multiple TBM breakthroughs due around the new year of 2018. The Changi bound tunnel was completed at Orchard last month, completing all bored tunnel works under the T219 project - the first project to do so along TEL3.

TBMs with envisaged completion between Dec 2017 and Jan 2018:
T209 TBM 1&2
T212 TBM 1
T215 TBM S-936
T227 TBM 1
T228 TBM 1

TEL1/2 November Tunnel Progress (No change since Sep)