Monday 11 September 2017

Lentor Cast (IV)

Excavation works for the station appears to have completed with structural works taking place at the platform level. Casting of the entrances are progressing, with the first superstructure emerging from Entrance D. Both TBMs are advancing through rock around Block 174 beneath AMK Avenue 4 and is targeted to breakthrough by December.


Lentor Station
Ent C,D & E
Entrance E
RC works from subway to ground level
Waterproofing to the completed roof of the underpass

Launch Shaft
Entrance C base slab RC works


Entrance D superstructure works







5XO Site
Changi bound tunnel

Tunnel roof slab cast


Main drive of Changi bound TBM from 5XO to Mayflower




Woodlands bound tunnel

No comments:

Post a Comment

Note: only a member of this blog may post a comment.