Sunday 5 March 2017

Tagore Cast (IV)

Structure of the concourse slab is mostly completed for the station box. TBM B drive is over 85% completed now and breakthrough at Springleaf is expected in early Q2. TBM C2 will follow suit a quarter later. Staging works for trackwork will commence at Tagore by year end with handover of site possession to CTCI at the later part of the year.


Concourse slab cast at Tagore



No comments:

Post a Comment

Note: only a member of this blog may post a comment.