Saturday 25 March 2017

Napier Excavation

Bored pile works have completed at the station and excavation works progresses.


Excavation works at station

Friday 24 March 2017

Stevens D-walls (V)

The second portion of the stage 3 traffic diversion works had been implemented along Stevens Road last week, allowing for the construction of the remaining half of the station's diaphragm wall. Excavation works have commenced at Entrance C&D. 

The project's first tunnel completion for the 300m southbound tunnel between Dalvey LS and the station is due next week (TBM 4). Lack of soil profile understanding beneath private properties and portions of unfavorable geological conditions are hindering the tunnel progress towards Napier, as well as between Mount Pleasant and Stevens station.


Commencement of excavation works at Entrance C&D & Rectangular TBM launch shaft

Thursday 23 March 2017

Mount Pleasant Cast

The platform and mezzanine levels of the station have been cast and RC works will progress up to the concourse level in the next quarter. TBM S-936 has also completed the first Changi bound tunnel towards Caldecott earlier this month.


Mount Pleasant Station

Friday 10 March 2017

Caldecott Cast (III)

RC works for the station structure is progressing up to the concourse level.


Cross beams cast at Mezzanine 2 level (GL9.5-11.5)

Thursday 9 March 2017

Piling at Upper Thomson (II)

Diaphragm wall structure for the station is finishing up and construction of the roof slab is being done. TBM 1 has completed its first drive to Upper Thomson station and relaunch for the second drive is being prepped.


D-wall, bored pile, JGP, WSM and excavation works for roof slab construction taking place concurrently at Upper Thomson

Wednesday 8 March 2017

Bright Hill Excavation

Excavation works are in full swing at the station box. RC roof of the north cut and cover tunnel has also been cast. Main drive of the 4 TBMs are progressing and should be completed from the end of Q3 2017 onwards.


Excavation works in full swing at the station box

Tuesday 7 March 2017

Mayflower Cast (III)

Basic structure of the entrances are progressively completing accompanied by backfilling works on the surface.


Entrance D backfill & casting of surface perimeter

Monday 6 March 2017

Sunday 5 March 2017

Tagore Cast (IV)

Structure of the concourse slab is mostly completed for the station box. TBM B drive is over 85% completed now and breakthrough at Springleaf is expected in early Q2. TBM C2 will follow suit a quarter later. Staging works for trackwork will commence at Tagore by year end with handover of site possession to CTCI at the later part of the year.


Concourse slab cast at Tagore

Friday 3 March 2017

Springleaf Cast

RC works for the platform and concourse level are taking place at the station box following the completion of excavation works.


Excavation works completed at the Springleaf station

Thursday 2 March 2017

Facility Building - TBM 3 Breakthroughs

Piling works have recommenced at the facility building site, this time for the superstructural works. TBM 3 has broken through the facility building site from SBAB, while TBM 4 is meters away beneath the Mandai Lake Flyover awaiting settlement remedial actions. TBM 1 and 2 from Springleaf have almost reached the facility building and would complete by the 2nd quarter.


TEL1&2 Tunnel Chart, March 2017
Site filled back for bored pile works for facility building

Wednesday 1 March 2017

Mandai Depot - TBM 3 Second Breakthrough

Tunnelling works for the T206 project are wrapping up with 8 of the 10 bored tunnels completed. Cross passage excavation and the first stage concreting works are taking place within the tunnels. Structural, fittings and trackworks are progressing at the depot.


Stabling Yard nearing structural completion