Lateral bracing along the first strut layer have commenced along the station box commencing the excavation process. The north launch shaft has reached the formation level and installation of the tunnel eye together with lowering and assembly of the EPBM will take place in the next quarter.


Completion of the diaphragm wall at Great World station and commencement of strutting for bulk excavation
Strutting for the entrance linkway at River Valley Road


Formation level reached at the north shaft







Great World City entrance
Excavation of the south launch shaft

A temporary shed has been constructed over the delivered herrenknecht TBM segments