Tuesday 15 December 2015

Lentor Excavation (II)

Excavation to the basement roof slab of the Lentor station has completed and RC works are currently prepared for the subsequent concreting. The zone 1A section that had been concreted in September has been de-strut and backfilled, which made way for a minor realignment of Lentor Loop for the remaining d-walling works to be facilitated north.

Excavation of the launch shaft has completed and the RC works for the base slab is being carried out. The pre-assembled gantry beam is present at the portal surface. Phase 1 of the subway link beneath Yio Chu Kang Road has been backfilled and the sheet piles are currently being extracted.

The project team has begun preparations for the impending second realignment of this intersection.


Aerial view of Lentor Station
Extraction of sheet piles at the completed subway



Preparations for the next intersection realignment (centre medians have been filled with asphalt to the top and bottom of the picture)
Acoustic barriers installed at the Calrose facade (right). Works on the entrance will begin after the junction has been realigned.

Gantry crane segments at the launch shaft

RC works at the base slab




Excavation of the roof slab earlier this month (Ricardo)


Zone 1A backfilled

D-walling and strutting at the north



5XO Excavation (II)


Excavation for the Changi bound side of the structure has reached beneath the 3rd strut level. The Woodlands bound side is still constructing the final diaphragm wall panels.


Top-down view of 5XO
Fissure grouting taking place for the ground treatment works at the breakthrough of the W/Bound tunnel











No comments:

Post a Comment

Note: only a member of this blog may post a comment.