Thursday, 1 February 2018

February Tunnel Progress

The T215 and T217 projects have successfully completed all tunnelling works this week with the docking of the 2 Herrenknecht Mixshield TBMs at Caldecott cripple siding tunnel and Napier stations respectively. 14 bored tunnel drives remain - bulk of which would only be completed in the second half of the year.

The next breakthrough will take place at Caldecott by TBM 3 under the T212 project around end Feb/early March. Its sister TBM 2 will subsequently arrive approximately 6 weeks later, concluding the tunnelling works for Stage 2 and TELC2 in April.


TEL1/2 Tunnel Chart (January 2018)

Friday, 29 December 2017

Gardens By The Bay - Tunnelling Completes

Tunnelling works for the T228 project have completed ahead of schedule, with the Hitachi Zosen EPBM breaking through the station d-wall from the return Changi bound tunnel drive earlier this month. RC works for the station's internal structure continues, with excavation works starting at entrance A. Preparations for the reinstatement of Marina Gardens Drive over the completed subway are in progress with implementation scheduled next quarter.


Gardens By The Bay station

Thursday, 28 December 2017

Marina South Cast (IV)

RC works for the internal structure of the station continues up to the roof slab. The TBM has completed the Woodlands bound drive to Marina Bay and reassembly works for the Changi bound drive have begun with the dismantling of the backup gantries & assembly of the heavy lift crawler crane on site. The relaunch of the TBM is scheduled next quarter - the 2nd last to be facilitated along the TEL1-3.


Marina South station