Friday, 10 November 2017

November Tunnel Progress

Bored tunnelling works progresses across the line, with multiple TBM breakthroughs due around the new year of 2018. The Changi bound tunnel was completed at Orchard last month, completing all bored tunnel works under the T219 project - the first project to do so along TEL3.

TBMs with envisaged completion between Dec 2017 and Jan 2018:
T209 TBM 1&2
T212 TBM 1
T215 TBM S-936
T227 TBM 1
T228 TBM 1

TEL1/2 November Tunnel Progress (No change since Sep)

Friday, 13 October 2017

Gardens By The Bay Cast (III)

Casting of the station structure is progressing at the concourse level up to the basement roof slab.


T228 Gardens By The Bay Station

Wednesday, 11 October 2017

Marina South Cast (III)

Excavation works for the station zone adjacent to the cut and cover tunnel are progressing down to the formation level. The first completed portion at the center of the station sees the structure cast all the way up to the basement roof slab. Bored tunnelling works on the Woodlands bound drive is on its main drive with a third of the progress completed.

Marina Mall was diverted at the T228 interface at the end of Q3 for the cut and cover tunnel construction adjoining the Gardens By The Bay Station. Backfilling works across the completed portion of the C&C tunnel are underway.


Structure progressing at Marina South