Saturday, 5 November 2016

November Tunnel Progress

Tunnelling works for the line have been ongoing for 15 months now. 11 bored tunnels have been completed.


TEL1/2 Tunnel Chart, November 2016
T202 - Breakthrough of TBM 2 at Woodlands Station on October 10. This is the first contract to complete all bored tunnel excavation

Friday, 14 October 2016

Gardens By The Bay - TBM Assembly

The Hitachi Zosen EPBM was lowered down the launch shaft in August and assembly works are underway beneath the road deck. Excavation works are mostly completed along the station box, and RC works have commenced for the base slab at the southern end.


T228 Gardens By The Bay station

Thursday, 13 October 2016

Marina South Excavation (IV)

Excavation works are nearly completed at the S5-S6 layer across the 20m deep station box and cut and cover tunnel.


Excavation works across the Marina South site