Saturday, 30 July 2016

July Tunnel Progress

Tunnelling works are underway along all the projects along stages 1 and 2 of the line, with the first slurry TBM for the T211 project launched at Bright Hill this week. 5 bored tunnels have been completed by the first half of the year and a further 5-8 tunnels are envisaged to complete by year end.

TEL1/2 Tunnel Chart, July 2016
T206 - Launch preparations for the second drive of TBM 4 for reception tunnel 1 at Sembawang Airbase C&C (Photo credits: LTA)

Saturday, 25 June 2016

Marina South Excavation (III)

Bulk excavation works are underway at the station and cut and cover tunnels. The remaining pipe pile construction is being carried out beneath the former Marina Boulevard.


Excavation works at the cut and cover tunnel